| Registered No. WB/SC-247 | No.WB(Part-I)/2007/SAR-62 |
|
![]() |
||
|
Extraordinary
|
||
|
Published
by Authority
|
||
|
|
||
| CAITRA 14] | WEDNESDAY,
APRIL 04, 2007 |
SAKA 1929 |
|
|
| PART
I - Orders and Notifications by the Governor of West Bengal, the High
Court, Government Treasury, etc. |
No. 34/WBERC Dated:
04.04.2007
In exercise of the
powers conferred by sub-section (1) and clause (zp) of sub-section (2) of
section 181 read with clause (h) of sub-section (1) of section 86 of the
Electricity Act, 2003 (36 of 2003) and all powers enabling it on that behalf
and in supersession of the Notification No. 26/WBERC dated 12th
January 2006 published in the Kolkata Gazette, Extraordinary on 16th
January 2006, the West Bengal Electricity Regulatory Commission (WBERC)
hereby makes the following Regulations.
CHAPTER – I
GENERAL
1.1 Short title, commencement and interpretation:
I.
These Regulations
may be called the West Bengal Electricity Regulatory Commission (State Electricity
Grid Code) Regulations, 2007 or in short WBEGC.
II.
These Regulations
shall come into force on the date of their publication in the official gazette
unless otherwise stated in these Regulations and shall be concurrent within
the area of jurisdiction of the West Bengal Electricity Regulatory Commission.
1.2 Definitions:
1.2.1 In these Regulations, unless the context otherwise
requires:
(i)
“Act” means the Electricity Act,
2003;
(ii)
“Agency / Entity” means Agency / Entity as specified
in Tariff Regulations;
(iii)
“Area Load Despatch Centre” or “ALDC” means Area
Load Despatch Centre which may be declared as such by SLDC with the approval
of the Commission;
(iv)
“Automatic Voltage Regulator” or “AVR” means a
continuously acting automatic excitation control system to control the voltage
at the generator terminals of a generating unit;
(v)
“ABT” means Availability Based Tariff as specified
in the Tariff Regulations;
(vi)
“Beneficiary” means an agency who draws and /
or injects power from / to State Grid;
(vii)
“Black Start Procedure” or “BSP” means the procedure
necessary to bring back normalcy in the grid from a black out;
(viii)
“Bilateral Exchange of Power” means exchange of
power under any agreement between the persons as allowed under the Act;
(ix)
“CCGT” means Combined Cycle Gas Turbine;
(x)
“CEA” means Central Electricity Authority;
(xi)
“Commission” means the ‘West Bengal
Electricity Regulatory Commission’ in short, called WBERC;
(xii)
“Constituent” means any Agency / Entity connected
to the State Grid system;
(xiii)
“CPP” means Captive Generating Plant as specified
in Tariff Regulations;
(xiv)
“CTU” means an Central Transmission
Utility;
(xv)
“Demand” means the demand of active power in MW,
reactive power in MVAR and apparent power in MVA of electricity unless otherwise
mentioned;
(xvi)
“Distribution Licensee” means a
person exempted either under section 13, or under section 8, or a person
who has been granted a licence by the Commission under section 14 of the
Act including a deemed licensee under first, third, fourth and fifth proviso
to the section 14 of the Act to distribute electricity within its area of
supply;
(xvii)
“Disturbance Recorder” or “DR” means a device
provided to record the behaviour of the pre-selected parameters of the system
during an event;
(xviii)
“EHT” means extra high tension
or extra high voltage (EHV) when the voltage exceeds 33000 Volts, subject,
however, to the percentage variations allowed by Safety Regulations;
(xix)
“Entity” means entity as defined
in Tariff Regulations;
(xx)
“Event” means an
unscheduled or unplanned occurrence on a Grid including faults, incidents,
breakdowns and forced outage;
(xxi)
“Event Logger” or “EL” means an automatic device
provided to record the sequence of operation in time, of the relays/equipments
at a location during an event;
(xxii)
“Ex-Power Plant” means net sent out of a generating
station in MW/MWH measured at all outgoing lines / feeders from the generating
station;
(xxiii)
“Fault Locator” or “FL” means a device installed
at the end of a transmission line to measure/indicate the distance at which
a line fault may have occurred;
(xxiv)
“Force Majeure” means any event which is beyond
the control of the parties which they could not foresee or with a reasonable
amount of diligence could not have foreseen or which could not be prevented
and which substantially affect the performance by either party such as but
not limited to: -
(a)
Natural phenomena, including but not limited to
floods, droughts, earthquakes and epidemics;
(b)
Acts of any Government, domestic or foreign, including
but not limited to war declared or undeclared, hostilities, priorities,
quarantines, embargoes;
(c)
Riot or Civil commotion;
(d)
Grid’s failure not attributable to parties;
(xxv)
“Forced Outage” means an
outage of a Generating Unit or a transmission facility due to a fault or
other reasons, which has not been planned;
(xxvi)
“Generating Station” means Generating Stations
including CPPs.
(xxvii)
“Governor Droop” means in relation to the operation
of the governor of a Generating Unit, the percentage drop in speed which
would cause the Generating Unit under free governor action to change its
output from zero to full load;
(xxviii)
“GT” means Gas Turbine;
(xxix)
“HT” means High Tension (HT) or High Voltage (HV)
where the voltage exceeds 650 Volt but not exceeds 33,000 volts under normal
conditions, subject, however, to the percentage variation allowed under
the Safety Regulations;
(xxx)
“Inter State Generating Station” or “ISGS” means
a generating station owned by any generating company in which two or more
than two States have a share and whose scheduling is to be coordinated by
the RLDC concerned;
(xxxi)
“IE Rules” means Indian Electricity
Rules, 1956;
(xxxii)
“Licensee” means a person who has
been granted licence by the Commission under section 14 of the Act for distribution
and / or transmission of electricity and also includes a deemed licensee
under first to fifth proviso to section 14 of the Act or persons exempted
under section 13 or section 8 of the Act in the State;
(xxxiii)
“LNG” means Liquefied Natural Gas;
(xxxiv)
“LT” means Low Tension (LT) or
Low Voltage (LV) where the voltage does not exceed 250 Volts, subject, however,
to the percentage variations allowed under the Safety Regulations;
(xxxv)
“Maximum Continuous Rating” or
“MCR” means the Maximum Continuous Rating
as specified in the Tariff Regulations;
(xxxvi)
“MT” means Medium Tension or Medium Voltage (MV)
where the voltage exceeds 250 volts but does not exceed 650 volts under
normal condition, subject, however, to the percentage variations allowed
under Safety Regulations;
(xxxvii)
“Open Access Customer” means the Open Access Customer
as defined in Open Access Regulations;
(xxxviii)
“Open Access Regulations” means the Open Access
Regulations as specified in Tariff Regulations;
(xxxix)
“Open Access Source” means Open Access source
as specified in Open Access Regulations;
(xl)
“Pool Account” means an account to be prepared
and operated by SLDC for payments regarding Unscheduled Interchanges and
reactive energy exchanges in the State grid;
(xli)
“Power Purchase Agreement” or “PPA” between the
entities means the commercial agreement between two agencies for the purchase
/ sale of power;
(xlii)
“REF Relays” means Restricted Earth Fault Relay;
(xliii)
“Regional Grid” means the entire synchronously
connected ‘Regional Grid’ specified in the Grid Code and concerned to the
territorial jurisdiction for which RLDC has been established;
(xliv)
“Regulations” means the Regulations made under
the Act;
(xlv)
“RLDC” means Regional Load Despatch Centre concerned
to the territorial jurisdiction under which State is being considered in
accordance with sub-section (1) of section 27 of the Act;
(xlvi)
“RPC” means Regional Power Committee concerned
to the Region under which State is being considered in accordance with the
resolutions under clause (55) of section 2 of the Act;
(xlvii)
“Rules” means the Rules made under
the ‘Act’ by the State Government;
(xlviii)
“ROR” means Run of the River;
(xlix)
“Safety Regulations” means Regulations
framed by Authority under section 53 of the Act or Indian Electricity Rules,
1956;
(l)
“SLCF” or “State Level Co-ordination
Forum” means a committee constituted by the Commission through modification
with one member each from licensees and generating companies having installed
capacity above 1000 MW connected to the STS where the convener and Chairman
of the forum will be notified by the Commission during constitution of the
forum;
(li)
“SLDC” means SLDC as specified in Tariff Regulations;
(lii)
“Spinning Reserve” means reserve margin of part
loaded generating capacity that is synchronized to the State Grid and is
ready to provide increased generation at short notice pursuant to despatch
instruction or instantaneously in response to a frequency drop;
(liii)
“Standing Committee” for transmission planning
means a committee constituted by the CEA to discuss, review and finalize
the proposals for ISTS and associated Intra-State Transmission Systems;
(liv)
“STS” or “State Transmission System” is consisting
of Intra-State Transmission System of the State comprising of transmission
lines of owners of dedicated transmission lines, STU and Transmission Licensees
in State grid;
(lv)
“STU” or “State Transmission Utility” means STU
as specified in Tariff Regulations;
(lvi)
“State” means State of
(lvii)
“State Government” means Government
of West Bengal;
(lviii)
“State Grid” to be mean the entire synchronously
connected grid of power system of the State including the State Transmission
System along with the connected grid of the Distribution Licensee with embedded
generating stations, if any;
(lix)
“Static VAR Compensator” or “SVC” means an electronically
controlled facility designed for the purpose of generating or absorbing
reactive power;
(lx)
“Tariff Regulations” means the Regulations framed
by the Commission under section 61 of the Act;
(lxi)
“Transmission Licensee” means Transmission
Licensee as specified in Tariff Regulations;
(lxii)
“Transmission System” mean the
transmission system as specified in the Tariff Regulations;
(lxiii)
“User” means a person
/ agency using the Intra-State Transmission System;
(lxiv)
“VAR” means Reactive Power;
(lxv)
WBSEB means WBSEB as specified in Tariff Regulations;
1.2.2 Words and expression used and not defined in
any of the Regulations shall have the meanings as defined in the Act.
1.3
Applicability:
1.3.1
These Regulations are applicable
to SLDC, ALDC and all the entities connected to the State Grid and under
the purview of WBERC. In case of any inconsistency between the Grid Code
and State Grid Code, the provision of Grid Code shall prevail.
1.3.2
In case of any inconsistency between
Grid Standard and State Grid Code, the provision of Grid Standard shall
prevail.
1.4
Introduction Objective, Structure and Functional Responsibilities:
1.4.1 Introduction:
1.4.2 Objective:
The WBEGC lays down
(i)
the principles, the guidelines and
standards to be followed by various agencies and participants in the system
to plan, develop, expand, maintain and operate the State Grid in most efficient,
equitable, reliable, safe and economic manner;
(ii)
suitable measures for connectivity
with State Grid for all generating stations, transmission licensees, and
distribution licensees;
(iii)
the standard of the service for compliance
by all participants with regard to quality and reliability;
(iv)
the ways and means of planning of the
State Transmission System and its development;
(v)
the methods of operation of the State
Grid under normal, abnormal and emergency conditions;
(vi)
makes room for documentation of the principles
and procedures, which define the relationship between various users of the
STS and SLDC;
(vii)
facilitates beneficial open access
of electricity by providing a common basis of operation of STS applicable
to all users of the system;
(viii)
ensures economy and efficiency in the
operation of the State Grid in the State and to achieve compliance with
the grid standard on direction of SLDC by every licensee and others involved
in operation of the State Grid;
1.4.3 Functional Responsibilities:
The functions of
STU, SLDC, entities and consumers shall be consistent with the provisions
of the Act. As relevant to State Grid Code, their functions shall be as
follows:
(i)
State Transmission Utility (STU):
(a) The STU shall play the main role for evacuation
of power generated by generating stations that are connected to the STS,
supply of power to entities engaged in distributing electricity, exchange
of power among entities and exchange of power through inter-connection with
CTU.
(b) The STU shall also be responsible for coordinating,
managing and servicing of the State Grid Code.
(c) It shall also discharge functions of planning
and co-ordination relating to STS with due co-relation with CTU, State Government,
Entities, RPC, CEA, and any other person notified by the State Government.
(d) It shall ensure development of an efficient,
co-ordinated and economical system of Intra-State transmission lines for
smooth flow of electricity from a generating station to the load centres.
(e) The STU shall also be responsible for providing
non-discriminatory open access to its transmission system subject to availability
of adequate transmission facility for use by any licensee or generating
station or any Open Access Customer on payment of necessary transmission
charges, other charges, fees and surcharges as provided in different Regulations
specified by the Commission.
(ii) State Load Despatch Centre (SLDC):
The SLDC shall be
the apex body in the STS operation to ensure integrated operation of the
State Grid in the following manner:
(a)
The SLDC shall give such directions
and exercise such supervision and control not inconsistent with the provisions
of the Acts, Regulations, Codes and Standards made thereunder, as may be
required for ensuring secured and integrated operation of the State Grid,
as also for achieving maximum economy and efficiency in the operation of
the latter.
(b)
The SLDC shall comply with such principles,
guidelines and methodologies in respect of transmission and wheeling
and optimum scheduling and despatch of electricity as may be specified
in the WBEGC and other Regulations specified by the Commission.
(c)
All directions issued by the RLDC to
any transmission licensee or owner of dedicated transmission lines in the
State Grid or generating station in the State shall be issued through the
SLDC.
(d)
The SLDC shall also be responsible
for scheduling and dispatch of electricity in accordance with the contracts
entered into with the entities operating under the purview of WBERC.
(e)
Further, the SLDC shall be responsible
for real time monitoring grid operations, keeping accounts of the quantity
of electricity transmitted through the State Grid, carrying out real time
operation for grid control and despatch of electricity within the region
concerned to the RLDC through secured and economic operation of the State
Grid in accordance with the Grid Standards and WBEGC within the State, and
exercise supervision and control over the STS.
(f)
All entities and substation(s) in the
State Grid shall comply with the direction by the SLDC.
(iii) Distribution Licensee:
A distribution Licensee
shall inform the STU and the SLDC about the contracts entered into for importing
/ exporting power from/to different sources and shall assist and co-ordinate
with the SLDC in real time operation, control of the system and drawal /
injection of reactive power from / to the STU. Distribution licensee shall also assist / follow
instruction of the SLDC in scheduling its exchange from / to the STU.
(iv)
Transmission Licensee / Owner of dedicated transmission line:
Every transmission
licensee or owner of a dedicated transmission line of the State grid shall
comply with such technical standards of operation and maintenance of transmission
line, as applicable to the Intra-State Transmission System, in accordance
with this WBEGC, Grid Standards and Grid Code.
(a)
It shall maintain
and operate the part of the STS which are licensed to transmission licensee
and comply with directions of SLDC.
(b)
It shall provide
non-discriminatory open access in pursuance to open access to its transmission
system subject to availability of adequate transmission facilities for use
by any licensee or generating company or open access customer on payment
of the charges as determined by the Commission.
(v)
Generating Station:
The generating stations
connected to the STU and evacuating their generation through the STU, shall
inform the STU and the SLDC about the contracts entered into with different
parties for exporting power along with its schedule. They should follow
the instruction of the SLDC and assist the SLDC in the real time operation
and control of the system and scheduling of generation.
(vi) Free Governor Action:
(a)
All units of generating stations having
capacity above 50 MW shall keep their governor under free governor operations
as per WBEGC with effect from the date to be separately notified by the
Commission.
(b)
If any entity seeks an exemption from
the above requirement, it shall file a petition justifying the same in advance
to the Commission, which may, at its sole discretion, allow the same.
(c)
The gas turbines / CCGT and nuclear
power stations shall be exempted from regulations 4.2.5, 4.2.6, 4.2.7 and
4.2.8 till the Commission reviews the situation.
CHAPTER 2
STATE TRANSMISSION SYSTEM PLANNING
2.1 Introduction
In accordance with clause (b) of sub-section
(2) of section 39 of the Electricity Act 2003, the STU shall discharge all
functions of planning and co-ordination relating to STS with CTU, State
Government, CEA, RPC and other related organizations, who shall utilize
the STS for evacuation or injection or drawal of power.
2.2 Planning
Procedure:
2.2.1 Load
Forecasting:
Power Supply Planning starts with a forecast
of anticipated future load requirements of both demand and energy covering
a particular period of time. The primary responsibility of load forecasting
rests with the distribution licensees, who shall follow the respective perspective
plans as per Tariff Regulations. The overall peak and energy demand projections
for such forecasts shall take into account the growth trend of the last
five years with due importance and weightage being given to growth in sale
of electricity for different classes of consumers in the said period. The
proposed services for connected load of 1 MW and above shall also be separately
considered for two categories viz. firm load in pipeline where investment
in infrastructure has already taken place, and infirm load where investment
decision is in the planning stage. This input shall be obtained from the
distribution licensee(s) concerned. Details for firm load including the
degree of firmness in terms of financial tie up and different agreement
signing may be recorded for proper assessment of the possibility of additions
of the demand in the system. Consideration of infirm load for overall load
forecast shall be based on the past experience of maturity rate for last
five years of such forecasted infirm load into reality. The load forecast
shall be consolidated transmission sub station wise (132 kV and above).
The periodicity of the survey shall preferably synchronize with the studies
conducted by CEA. The STU may conduct the load survey at shorter intervals
of time if the trend of growth rate shows an increase in two consecutive
years. The distribution entities shall furnish the required data to the
STU as required by the STU. The STU shall integrate the load forecasts and
determine a relatively long-term (10 years) load forecast for the State.
The resulting overall load forecast including its spatial distribution should
be one of the basis for expansion of generation and transmission and distribution
system. The planning process shall consider an extended study period of
10 years beyond the base period of 10 years. This load forecast along with
a note on such forecasting methodology may be submitted to the Commission
for approval before any planning on the basis of such forecast.
2.2.2 This load forecast along with demand growth
trend of different Districts and Municipal Corporations are to be provided
in the Website of the STU.
2.2.3 Planning:
2.2.3.1 The technical component of transmission and distribution
losses shall be estimated based on sample studies, measurements, load flow
studies etc. The STU shall work out on the basis of projected loads and
losses of the system, the net energy requirement and peak load requirement
at generation end. The installed capacity, peak availability, surplus or
deficit both in demand and in availability of energy at the State level
shall also be worked out by the STU. The demand forecasts as per Regulation
2.2.1 shall be used to determine the capacity of generation, transmission
and distribution systems and energy forecast along with the load duration
curve shall be used to determine the type of generation facilities required.
The generation criteria based on operational parameter as per Tariff Regulations
shall be applied for arriving at the additional generation capacity
requirement. While calculating the availability for existing units, the
trend of generation shall be considered and for projects under construction,
80% availability shall be considered. For any proposed hydro-generating
station, generating capacity shall be considered on a case specific basis
after considering the results of requisite detailed investigation studies.
2.2.3.2 The STU shall workout the requirement of additional
transmission capacity after taking into account, the existing capacity,
future requirement of power evacuation from new power generating projects
inclusive of CPPs, power generating projects under construction in State,
and share allocation of the State from ISGS. Any supply from generating
stations of temporary nature shall not be considered. In addition, the power
procurement plan of different distribution licensee of the State pursuant
to the Tariff Regulations and power to be wheeled by different Open Access
Customers in Long-Term Open Access as per Open Access Regulations shall
also be taken into account for the purpose of overall planning. Consumers
having open access of 1 MW and above under Short-Term Open Access shall
also be contacted to assess their likely demand from the State Grid and
degree of firmness of such demand to meet its regular supply as consumer
on expiry of such Short-Term Open Access or back-up or stand-by power as
specified in Open Access Regulations. Information from such consumer having
open access shall be collected in writing by the Distribution Licensee with
whose distribution system the premises of consumer is connected when the
Distribution Licensee prepares its perspective plan in pursuance of regulation
2.5.5 of Tariff Regulations. In the case of absence of any response from
such a consumer, it shall be treated that such a consumer has no requirement
of back up or stand-by power or any power against regular supply in consumer
mode on expiry of the terms of open access during the period of perspective
plan for which information is sought for. Such future demand for stand-by
or back-up power or regular supply for such consumer having open access
shall only be taken into consideration for the forecast demand only after
execution of agreement between the licensee and such consumer. The STU shall also identify suitable locations
near which big sub-station required to be installed. Regarding transmission
corridor availability, the norms as per Tariff Regulations shall be considered
and for adequate redundancy for secure and stable grid operation of the
STS, 30% extra capacity is to be created than the required capacity.
2.2.3.3 The STU shall carry out planning process from
time to time as per the requirement for identification of major Intra-State
Transmission System, which shall fit in with the perspective plan developed
by State Government. While planning, the following shall be considered in
addition to the data of authentic nature collected from and in consultation
with various generating stations, licensees, State Government, etc.
i)
Long Term Perspective Plan developed by CEA;
ii)
Latest Electric Power Survey report of CEA;
iii)
Transmission planning criteria, generation expansion
planning criteria and guidelines issued by the CEA;
iv)
National Electricity Plan, issued by Govt. of India,
which are relevant for development of STS;
v)
Any other authentic report on demand forecast carried
out by agencies like Advisory Board on Energy (ABE), Planning Commission,
CERC, WBERC, Govt. of West Bengal;
vi)
Capacity addition utilizing renewable energy resources;
vii)
System strengthening schemes – Need for which may
arise to overcome the constraints in power transfer and to improve the overall
performance of the State Grid;
viii)
Plans prepared by CTU in order to plan for evacuation
of power as required for STS or the State.
2.2.4 The plan shall indicate and include a chapter
on proposed STS scheme open for private investment by the STU, based on
which the entrepreneurs can formulate primary investment decisions.
2.2.5 The planning report shall indicate the action
taken to fulfill the additional requirements and actual progress made on
new schemes. These reports will be available to any interested party for
making investment decision / connection to the STS.
2.2.6 As voltage management plays an important role
in the STS, special attention shall be accorded to planning of VAR compensation
in the network so that voltage instability does not occur and line can transfer
designed power with designed operating voltage range.
2.2.7 Based on the load forecast and the additional
generation required for 10 years period the STU shall develop a long-term
plan for STS considering generation capacity addition programme and expansion
in distribution system.
2.2.8 Medium Term Planning: A 5 year rolling plan
shall also be finalized by the STU every year for requirement arising
out of expansion of the STS, generation and distribution systems to meet
the future demand and to ensure quality supply to consumers. The rolling
plan shall take into account the previous years’ achievements.
2.3 Planning
Criteria:
The planning criteria are based on the security
philosophy on which the STS is planned. The guidelines in general are detailed
for distribution, transmission and generation are to be as follow:
2.3.1 Distribution:
i)
The distribution system shall be developed to meet
the load demand of all existing consumers and intending consumers seeking
connection for supply including programme of intensification and virgin
area electrification. The distribution system is to be planned based on
load forecast and its spatial distribution. Power flow studies shall be
carried out wherever necessary. The perspective plan as per Tariff Regulations
shall be evolved for achieving target levels in aspects like reduction of
losses by proper choice of the length and size of Low Tension (LT) lines,
improvement of power factor, voltage control, etc.
ii)
Separate High Tension (HT) overhead feeders are to
be planned to cater to discrete load blocks to facilitate load management
during emergency operations. Use of sectionalisers or other devices to reduce
interruption is to be progressively introduced.
iii)
The distribution system shall have alternative feeding
arrangements for high load density areas and for essential services wherever
possible.
iv)
In addition to catering to the active power demand,
reactive power components of power requirement should be studied and adequate
VAR compensation are to be installed at different voltage levels to improve
power factor and cause reduction of losses. The distribution company in
their supply conditions shall include installation of reactive compensation
at load end depending on the type of load used.
v)
Voltage in the distribution system shall be controlled
and maintained at statutory levels. Voltages at the consumer terminals shall
be maintained as specified in the Safety Regulations.
vi)
The level of harmonics generated by consumer’s equipment
is to be controlled as per the limits specified in the grid connectivity
standards specified by CEA.
vii)
Voltage flickers caused by consumers’ loads shall
have to be controlled within the permissible limits as per Grid Standards.
2.3.2 Transmission :
2.3.2.1 Permissible
limits :
i)
The permissible voltage excursions for transmission
and sub transmission system during the steady state operation is +
5% for 400 KV and 220 KV level and + 10% for 132 KV and below. This
limit may be exceeded only during the outages of 400 KV lines and in such
cases, use of dynamic VAR source may be considered if necessary.
ii)
The standard fault rating of switchgear at 132 KV
is 31.5 KA and at 220 KV and 400 KV is 40 KA.
iii)
The capacity of any single sub station shall not normally
exceed 1000 MVA for 400 KV, 500 MVA for 220 KV and 250 MVA for 132 KV.
iv)
Size and number of EHT/HT transformers in a substation
of a transmission system shall be planned in such a way that in the event
of outage of any single unit, the remaining unit(s) would still supply the
load for 80% time of the day.
v)
The line loading limits shall be based on the thermal
/ surge impedance loading depending on the line sections and VAR support
provided.
2.3.2.2
Contingencies
(Under steady state conditions):
a) The
general policies are as given below:
i) As a general rule, the STS shall be capable
of withstanding and be secured against the following contingency outages
without necessitating load shedding (except for radial line) or rescheduling
of generation during steady conditions in operation: -
-Outage of a 132 KV D/C line (except for radial lines)
or,
-Outage of a 220 KV D/C line (except for radial lines)
or,
-Outage of a 400 KV S/C line (except for radial
lines)
or.
-Outage of single interconnecting transformer.
ii) The above contingencies shall be considered
assuming a pre-contingency system depletion (planned outage) of another
220 KV D/C line or 400 KV S/C line in another corridor and not emanating
from the same substation & during the period other than the peak.
iii) All the generating units of a generating
station may operate within their reactive capability curves and the network
voltage profile shall also be maintained within voltage limits specified.
b) The STS shall be capable of withstanding
the loss of the most severe single system in-feed transmission or generation.
c) Any one of these events defined above
shall not cause:
i)
prolonged operation of the system frequency below
and above specified limits;
ii)
unacceptable high or low voltage;
iii)
system instability;
iv)
unacceptable overloading of STS elements.
d) In all substations (132 KV and above),
at least two transformers shall be provided.
e) The STU shall carry out planning studies
for reactive power compensation of generating stations under WBERC purview
including reactive power compensation required at their switchyard.
2.3.2.3 Transient stability constraints:
The system shall be designed to maintain synchronism
and system integrity under the following disturbances:
i)
Outage of one of the largest size generating unit.
For this the generating companies should get clearance from STU regarding
the choice of unit size if the capacity of unit exceeds 500 MW.
ii)
A single line to ground fault on a 400 KV line, single
pole opening of the faulted phase (5 cycles) with unsuccessful reclosure
(dead time 1 sec) followed by three pole opening (5 cycles) of the faulted
line.
iii)
A permanent three phase fault with duration of 8 cycles
in 220 KV and 132 KV systems assuming three poles opening.
CHAPTER 3
CONNECTIVITY
CONDITIONS
3.1 General:
Connectivity conditions specify the minimum
technical and design criteria which shall be complied with by any agency
connected to, or seeking connection to the STS to transmit electrical energy
eitherway from/to the STS. The STU shall ensure compliance by any agency
with the above criteria as a pre-requisite for the establishment of an agreed
connection.
3.2 Procedure for Connection:
3.2.1
Prior to an agency being connected
to the STS, all necessary conditions outlined in the WBEGC and other Regulations
specified by CEA in addition to other mutually agreed requirements to be
complied with, must be fulfilled by the agency. Any agency seeking to establish
new or modified arrangement of connection to STS for use of it, shall submit
an application on specified format to the STU along with the following details:
i)
a report stating the purpose
of the proposed connection and / or modification, connection point, description
of apparatus to be connected or modification of the apparatus already connected
and beneficiaries of the proposed connection;
ii)
all prospective users shall
be required to pay to the STU all charges as specified by WBERC for the
purpose of conducting the initial interconnection studies, additional study
as well as for processing the application;
iii)
construction schedule and target
completion date;
iv)
a confirmation that the agency
shall abide by WBEGC and provisions of IE Rules or as may be specified in
the Regulations made by CEA under the Act.
3.2.1.2 The
STU shall normally make a formal offer to the agency within one month from
the date of receipt of all details along with the proposed changes, if any.
The offer shall stipulate and take into account any works required for the
extension or reinforcement of the transmission system to satisfy the requirements
of the connection application and for obtaining statutory clearances, way
leaves as necessary. The agency shall give its consent and submit to STU
within a fortnight thereafter.
3.2.1.3 Final
decisions on applications for connections to STU network shall be provided
by the STU within 45 days from the date of submission of consent to it by
the agency.
3.2.2
If the nature and complexity of the proposal is such that the specified
time limit for making the offer is not adequate, the STU shall make a preliminary
offer within the specified time limit indicating the extent of further time
required with the consent of the WBERC for more detailed examination of
the issues.
3.2.3
The STU shall make a revised
offer, upon request by any User, if necessitated by changes in data earlier
furnished by the User.
3.2.4
All offers (other than preliminary
offers) including revised offers shall remain valid for 60 days of issue
of the offer. In the event of the offer becoming invalid or not being accepted
by any User within the validity period, no further action shall be taken
by the STU on the connection applications. In the offer, details of the
requirements and procedures for connection to the STS and the resulting
Connection Agreement with the agency shall be set out.
3.2.5
Upon compliance, STU shall
notify the agency that it can be connected to the STS. However in case of
the existing connections between STS network and entities, the WBERC may
allow at its discretion relaxation up to one year in respect of connection
agreements and the present agreements/ present practice as followed may
continue in order to avoid the whole process of re-negotiation with the
existing entities.
3.2.6
Prior to providing any connectivity
to a consumer with the STS, the licensee shall take approval of the STU
and the SLDC after meeting all technical and commercial requirements of
the STU and the SLDC.
3.3 Connection Agreement:
A connection agreement shall include (but may not be limited to), as appropriate,
within its terms and conditions, the following:
i)
a condition requiring both
parties to comply with WBEGC and Grid Code;
ii)
the details of connection,
technical requirements and commercial arrangements;
iii)
the details of any capital
expenditure arising from necessary reinforcement or extension of the system
and demarcation of the same between the concerned parties;
iv)
a Site Responsibility Schedule;
v)
the metering arrangements;
vi)
the general procedure, guidelines,
etc. on protection and telemetry;
vii)
the procedures necessary for
site access, site operational activities and maintenance standard for equipment
of Licensee at the premises of the User and vice-versa;
viii)
commitments to provide data
requirement as per Annexure - I.
3.4 Connection Point:
3.4.1
Different requirement of connection
point of the STS with different constituents are as follows:
(i)
For Generating Station, the
switchyard voltage of connection point may be 400 / 220 / 132 KV or
as agreed with the Licensee with whose network the connection is to be effected.
Unless specifically agreed with the Licensee with whose network the connection
to be effected, the connection point shall be the outgoing feeder gantry
of generating station switchyard. All the terminals, communication, protection
and metering equipment owned by the generating company within the perimeter
of its site shall be maintained by it. From the outgoing feeder gantry onwards,
all electrical equipment shall be maintained by the Licensee or the owner
of the dedicated transmission lines with whose network the connection is
to be effected.
(ii)
For Distribution Licensee,
the voltage of connection point may be as agreed with Generating Station
or the Licensee with whose network the connection is to be effected but
the same cannot be below 6 KV. The connection point shall be the outgoing
feeder gantry of Generating Station switchyard or the sub-station in case
of the Licensee. However, in case of connection with dedicated transmission
lines, it may be the point as agreed by the Distribution Licensee and the
owner of the dedicated transmission line. All the terminal, communication,
protection and metering equipment within the premises of the sub-station
shall be maintained by owner of the substation. From the outgoing feeder
gantry onwards, all electrical equipment shall be maintained by the respective
distribution entity.
(iii)
For the ISTS of the Regional
Grid, the connection point, protection scheme, metering scheme, metering
point and the voltage shall be in accordance with the mutual agreement between
owners of two connecting systems, until and unless they are specified by
CEA in its Regulations under the Act.
(iv)
For CPPs and EHT/HT Consumers,
voltage may be 220/132/66/33 KV or as agreed with Licensee with whose network
the connection is to be effected. Sub-stations, owned by CPPs and EHT /
HT Consumers, shall be maintained by them or as mentioned in the connection
agreement. The connection point shall be the feeder gantry on their premises
in case of EHT / HT consumers and at Licensee’s gantry in case of CPPs.
3.5 STS Parameter Variations:
3.5.1 General:
Instantaneous values of system frequency of the State grid and voltage
are subject to variation from their nominal value as provided in these regulations.
All agencies shall ensure that their plants and apparatuses requiring service
from / to the STS are of such design and construction that satisfactory
operation shall not be prevented by such variation.
3.5.2 Frequency Variations:
Rated frequency of the system shall be 50.0 Hz and shall normally be controlled
within the limits as specified in Grid Code.
3.5.3 Voltage Variations:
The variation of voltage may not be more than the voltage range specified
in the IE Rules as may be specified by CEA in its Regulations under the
Act. The agency engaged in sub-transmission and distribution shall not depend
upon the STS for reactive support when connected. To avoid need of exchange
of reactive power to/from the STS, the agency shall estimate and provide
the required reactive compensation in its sub-transmission and distribution
network for maintaining a cumulative power factor of 0.85, to 0.95 in order
to meet its full reactive power requirement, unless specifically agreed
to with the STU.
3.6 Equipment installed by Agency and STU at
Connection Points:
3.6.1 Sub-Station Equipment:
i)
All EHV outdoor switchyard
equipment shall comply with standard of Bureau of Indian Standards (BIS)
/ International Electro Technical Commission (IEC) / prevailing code of
practice.
ii)
All equipment shall be designed,
manufactured and tested and certified in accordance with the quality assurance
requirements as per IEC / BIS standards.
iii)
Each connection between an
agency and STS shall be controlled by a circuit breaker capable of interrupting,
at the connection point, the short circuit as advised by the STU in the
specific connection agreement.
3.6.2 Fault Clearance Times:
i)
The total fault clearance time,
for faults on agency's equipment directly connected to STS and for faults
on STS connected to agency's equipment, from fault inception to the circuit
breaker arc extinction, shall not be more than –
a)
100 milli seconds (ms) for
400 KV;
b)
160 milli seconds (ms) for
220 KV & 132 KV;
c)
160/400 milli seconds (1st /2nd
Zone).
ii)
Back-up protection shall be
provided for 132 kV system and above for required isolation / protection
in the event of failure of the primary protection systems provided to meet
the above fault clearance time requirements. If a Generating Unit is connected
to the STS directly, it shall withstand, until clearing of the fault by
back-up protection on the STS side.
3.6.3
Protection:
i)
Protection systems are required to be provided by all entities connected
to the STS and as specified by STU. These are required to isolate the faulty
equipments and protect the other components against all types of faults,
internal / external to them, within the specified fault clearance time with
reliability, selectivity and sensitivity. Protective relay settings shall
not be altered, or protection bypassed and / or disconnected, without consultation
and agreement of all the affected users. If protection is bypassed and /
or disconnected by agreement, then the cause must be rectified and protection
shall be restored to normal condition as quickly as possible. If agreement
is not reached, the electrical equipment, in question, shall be removed
from service forthwith in a case where it affects the security of the system.
Relay setting co-ordination shall be done by STU. The STU shall arrange
periodic meetings of the entities to discuss coordination of protection.
The STU shall investigate into any malfunctioning of protection or other
unsatisfactory protection issues. The concerned Licensees shall take prompt
action to correct any protection malfunction or issue as discussed and agreed
to in these periodical meetings.
In case of installation of any device,
which necessitates modification / replacement of existing protection relays
/ scheme in the network, such modification / replacement shall be carried
out by owner of respective part of the network. All agencies connected to
STS shall provide protection systems as specified in the connection agreement.
Relay setting coordination shall be done at State level by STU.
ii) Generating units and
generating stations requirement:
a)
A generating unit shall be
capable of continuously supplying its normal rated active / reactive output
within the system frequency and voltage variation range indicated at regulation
3.5.3 above, subject to the design limitations specified by the manufacturer.
b)
A generating unit shall be
provided with an AVR, protective and safety devices, as set out in connection
agreements.
c)
All Generating Units and associated
electrical equipment connected to the State Grid shall be provided with
adequate protection so that the State Grid does not suffer due to any disturbance
originating from the generating unit.
d)
Each generating unit shall
be fitted with a turbine speed governor having an overall droop characteristic
within the range of 3% to 6%, which shall always be in service.
e)
Each generating unit shall
be capable of instantaneously increasing output by 5% limited to 105% MCR
when the frequency falls. Sliding back to the previous MW level (in
case the increased output level can not be sustained) shall not be faster
than 1% per minute.
iii) Transmission
Line Requirements:
Every EHT line taking off from a generating station or a sub-station shall
have distance protection and back up protection as mentioned below. The
STU shall notify users of any changes in its policy on protection from time
to time.
(a) 400 kV Lines:
Three-zone non-switched Main-1 and Main-2 distance protection with different
technical philosophy shall be provided. In addition to the above, single
pole tripping and single shot single pole auto-reclosing after an adjustable
dead time shall be provided. There need be no other back up protection.
(b) 220 kV Line:
Three-zone non-switched distance protection with permissive inter trip
and a suitable back-up protection is to be provided. Single pole tripping
with single shot auto re-closing with adjustable dead time shall be provided.
(c) 132 kV Lines:
Three-zone non-switched distance protection with suitable back-up protection
is to be used.
For cable feeders - cable differential / suitable fast protection to be
used.
(d) General:
For short transmission lines alternative appropriate protection schemes
may be adopted.
(iv) Distribution Line Requirements:
All 33KV and 11/6 kV lines at connection
points shall be provided with a minimum of over current and earth fault
protection with or without directional features as given below:
(a)
Single Radial Feeders:
Non-directional time lag over current and earth fault relay with suitable
settings to obtain discrimination between adjacent relay stations;
(b)
Parallel Feeders/ Ring Feeders:
Directional time lag over current and earth fault relays;
(c)
Long Feeders / Transformer Feeders:
For long feeders or transformer feeders, the relays should incorporate
a high set instantaneous element.
(v) Transformer Requirements: Generator Step
up, Auto and Power Transformers:
All windings of auto transformers and power transformers of EHV class
shall be protected by differential relays and REF relays. In addition there
shall be back up time lag over current and earth fault protection. For parallel
operation such back up protection shall have directional feature. For protection
against heavy short circuits, the over current relays should incorporate
a high set instantaneous element. In addition to electrical protection,
gas operated relays, winding temperature protection and oil temperature
protection shall be provided. For transformers of HV class, differential
protection shall be provided for 10 MVA and above along with back up time
lag over current and earth fault protection (with directional feature for
parallel operations).
Transformers 2.5 MVA and above and less than 10 MVA shall be protected
by time lag over current, earth fault and instantaneous REF relays. In addition,
all transformers 2.5 MVA and above shall be provided with gas-operated relays,
winding temperature and oil temperature protection.
(vi) Sub-Station Bus Bar Protection and Fire Protection:
All users shall provide suitable bus bar protection for substation bus
bars in all 400 kV, 220 kV and 132 kV class substations or generating stations.
Adequate precautions shall be taken and protection shall be provided against
lightning and fire hazards to all apparatus of the users conforming to relevant
Indian Standard Specification and / or provisions as specified in Safety
Regulations.
3.6.4
Metering:
i)
The agency who has to provide,
operate and maintain the metering arrangements at various locations shall
be specified by the STU in the connection agreement.
ii)
Commercial Metering:
The commercial metering is designed to ensure the following:
(a)
to compute the actual net drawal
by the STU for the time blocks to be specified by the STU through reading
of special energy metering installed at all locations of interconnections;
(b)
to measure energy supplied
by the various generators;
(c)
to measure total energy supplied
to high-tension consumers at various voltages and to measure energy at substation
end of distribution feeders of the distribution licensees;
(d)
to measure the import and export
of energy into and from EHV level of State Grid system so as to arrive at
the losses at various voltage levels;
(e)
to measure the VAR flow at
various nodes of the grid;
(f)
to strike an energy balance
in each financial year.
iii)
Commercial metering details:
(a)
MW, MWH and MVARH flow are to be measured
at interconnection points, power transformer locations, distribution substation
end and consumption by HT / EHT consumers. The information are to be provided
in the specified formats. Each metering point associated with determination
of energy exported or imported shall be provided with both main and check
meter or as per the agreement between the STU and the entities. Minimum
standards of accuracy of such meter shall be of class 0.2 or as specified
by the STU. All current transformers and voltage transformers used in conjunction
with commercial (tariff) metering shall conform to the relevant BIS or standard
of IEC. These shall be of accuracy class having better accuracy than 0.5
and of suitable rating to cater to the meter and lead wire burden.
Voltage supply to the metering shall be assured with necessary voltage
selection schemes. Voltage failure relays shall be provided which shall
initiate alarms on loss of one or more phases of the voltage supply to any
meter. Meters shall be tested and
calibrated by a neutral agency in a frequency as specified by CEA or in
absence of such at least once in a year or such as mutually agreed between
the STU and the entities according to the guidelines in the standards /
supplier's recommendations. Records of meter calibration test shall be maintained
for future reference.
(b)
Wherever a meter becomes defective, consumption
recorded by the check meter shall be referred for a mutually agreed period.
The details of malfunctioning along with date, time and other data including
load survey data shall be retrieved from the main meter. The exact nature
of malfunctioning shall be brought out after analyzing the data so retrieved
and the consumption / losses recorded by the main meter shall be assessed
accordingly.
(c)
If the main as well as the check metering
systems become defective, the assessment of energy consumption for the outage
period shall be done by the concerned parties on mutually agreed basis.
(d)
A procedure shall be drawn up between the
STU and the entities covering summation, collection, processing tariff meter
readings at various connection sites. This may be revised from time to time
as needed.
(e)
The ownership and responsibility of maintaining
and testing of meters shall be mutually agreed between the entities and
the STU.
(f)
Any disputes relating to inter-entity metering
between the STU / Transmission Licensee and Generating Company / Distributing
Licensee / Open Access Users / Transmission Licensee shall be settled in
accordance with the procedures stipulated under relevant Power Purchase
Agreement / Connection Agreement as the case may be. In case of unresolved
dispute, the matter may be referred to WBERC for adjudication and reference
for arbitrations.
iv)
Operational Metering:
(a)
The Generating Company shall
install operational metering to STU's specification so as to provide operational
information for both real time and recording purposes in relation to each
generating unit at each power station in respect of bus voltage frequency,
MW, MVAR and any other additional data as required by STU.
(b)
All current transformers and
voltage transformers used in conjunction with operational metering shall
conform to the relevant standards and shall have accuracy better than accuracy
class 0.5 and of suitable ratings to cater to the meter and lead wire burden.
(c)
Meters shall be calibrated
so as to achieve overall accuracy of operational metering in the limits
as specified by the STU.
(d)
Records of calibration shall
be maintained for reference and shall be made available to the STU on request.
(e)
Generating companies shall
furnish recorded data of all electric measurements and events recorded by
the operational metering to the SLDC as requested by them.
(f)
The STU shall be responsible
to formulate the metering procedure and implement it with other users.
3.6.5 Data Requirements:
Users shall provide the STU with data for this section as specified in
the formats under Annexure – II.
3.6.6 Communication Facilities:
The following communication facilities as relevant and applicable to the
user shall be decided and finalized at the initial stage and incorporated
in the Connectivity Agreement:
(a) Audio Communication:
Reliable and efficient audio communication system shall be provided to
the SLDC / ALDC to facilitate supervision / control / direction of the State
Grid under both normal and abnormal operating conditions.
(b) Data Communication:
Real time telemetered data through Supervisory Control And Data Acquisition
System (SCADA) or Data Acquisition System (DAS) and off-line data for State
Grid such as flow, voltage, States of switches, transformer taps, etc. through
suitable and reliable data communication facilities so as to facilitate
efficient and uninterrupted data exchange with SLDC / ALDC under both normal
and abnormal operating conditions.
(c) Data Entry Terminals:
Data entry facilities as advised by SLDC for exchange of information between
SLDC and entities.
3.6.7
System Recording Instruments:
Recording instruments such as DAS / Disturbance Recorder / Event Logger
/ Fault Locator (including time synchronization equipment) shall be provided
in the STS for recording of dynamic performance of the STS. Agencies shall
provide all the requisite recording instruments as specified in the connection
agreement according to the agreed time schedule.
3.7 Reactive Power Compensation:
3.7.1
Reactive power compensation and / or other facilities, should be
provided by the STU or Transmission Licensees, etc. For agencies engaged
in distributing electricity reactive power compensation shall be provided
as far as possible in the low voltage systems close to the load points,
thereby avoiding the need for exchange of reactive power to / from STS and
to maintain STS voltage within the specified range.
3.7.2
Fixed line reactors may be provided to control temporary over voltage
within the limits as set out in connection agreements.
3.7.3
The addition of reactive compensation to be provided by the agency
(including generating station) shall be indicated by the STU in the Connection
Agreement for implementation on the basis of planning studies.
3.8 Responsibilities for Operational Safety:
The STU, the users, and the entities shall
be responsible for safety as indicated in Site Responsibility Schedules
for each connection point.
3.8.1 Site Responsibility Schedules:
i) A Site Responsibility Schedule shall
be produced by the parties as agreed in the connection agreement detailing
the ownership, control, maintenance and operational responsibilities of
each, before execution of the project or connection including safety responsibilities.
For connection to the STS, a schedule shall be prepared by the agency
pursuant to the relevant connection agreement which shall mention, for each
item of plant and apparatus at the connection point, the following:
Ø
Ownership of the plant / apparatus,
Ø
Responsibility for control of the plant / apparatus,
Ø
Responsibility for operation of the plant / apparatus,
Ø
Responsibility for maintenance of the plant / apparatus
and
Ø
Responsibility for all matters relating to the safety
of any person.
Ø
The incharge of the site.
ii)
The format, principles and basic procedures to be
used in the preparation of Site Responsibility Schedules shall be formulated
by the STU in line with the Regulation specified by the CEA for technical
standards for connection to grid and shall be provided to each agency /
entities for compliance.
iii)
All agencies connected to or planning to connect to
the STS shall ensure providing of Remote Transmitting Unit (RTU) and other
communication equipments, as specified by the SLDC, for sending real-time
data to the SLDC at least before date of commercial operation of the generating
stations or sub-station / line being connected to the STS.
3.8.2 Single Line Diagrams:
i)
Single Line Diagram shall be furnished to the SLDC
for each connection point with transmission licensee by the connected agencies
in concurrence with Transmission Licensee. These diagrams shall include
all HV connected equipment and the connections to all external circuits
and incorporate numbering, nomenclature and labelling, etc., The diagram
shall provide an accurate record of the layout and circuit connections,
rating, numbering and nomenclature of HV apparatus and related plant.
ii)
Whenever any equipment is proposed to be changed,
the concerned agency shall intimate the desired changes to the Licensee
with whom he is connected and to the SLDC. When the changes are implemented,
changed Single Line Diagram shall be circulated by
the agency to the SLDC and the STU.
3.8.3
Site Common Drawings:
i)
Site Common Drawing shall be prepared for each connection
point and shall include site layout, electrical layout details of protection
and common services drawings. The
detailed drawings for the portion each of the agencies concerned at each
connection point shall be prepared individually and exchanged between agencies
and STU.
ii)
The detailed drawings for the portion of the agencies
and the STU at each connection point shall be prepared individually and
copies shall be handed over to other party and the STU.
iii)
If any change in the drawing is found necessary, either
by agencies or the STU, the details shall be exchanged between agency and
the STU as soon as possible.
3.9
Procedure for Site Access, Site Operational Activities
and Maintenance Standards:
The connection agreement shall also indicate the procedures necessary
for site access, site operational activities and maintenance standards for
the STU equipment at the premises of the users and vice versa.
3.10 Schedule of assets at State grid:
The STU shall submit annually to WBERC by 30th September each
year a schedule of transmission assets, which constitute the State grid
as on 31st March of that year indicating ownership on which the
SLDC has operational control and responsibility.
CHAPTER 4
OPERATION OF THE STATE GRID
4.1 Operation Policy:
4.1.1
An integrated operation of the State grid is aimed at achievement
of overall operational economy and reliability of the State Grid.
4.1.2
Overall real time operation of the State grid shall be supervised
by the SLDC. The roles of the SLDC and the STU shall be in accordance with
WBEGC.
4.1.3
Such Distribution Licensee shall establish at least one ALDC to monitor
grid operation of its distribution system and to make coordination with
the SLDC.
4.1.4
All State entities shall comply with the operation guidelines specified
hereinafter and co-ordinate with each other, for deriving maximum benefits
from the integrated operation and for equitable sharing of obligations.
4.1.5
A set of detailed internal operating procedures for the State Grid
shall be developed and maintained by the SLDC in consultation with the entities
and the same shall be consistent with WBEGC.
4.1.6
The control rooms of the SLDC, ALDC, generating stations, and EHV
sub-stations and any other control centers of all the entities shall be
manned round the clock by qualified personnel with adequate training.
4.2 System Security Aspects:
4.2.1 All entities in the State grid shall endeavor
to operate their respective State Grids and generating stations in synchronism
with each other at all times, such that the entire State grid operates as
one synchronized system.
4.2.2
(i) No part of the State
grid shall be deliberately isolated from the rest of the State Grid, except
-
a)
under an emergency, and conditions
in which such isolation would prevent a total grid collapse and / or enable
early restoration of power supply;
b)
when serious damage to a costly
equipment is imminent and such isolation would prevent it; and
c)
when such isolation is specifically
instructed by SLDC.
(ii)
Such isolation due to any of the above mentioned causes under (i)
shall be followed by complete restoration of synchronized grid as soon as
the conditions again permit. The restoration process shall be supervised
by the SLDC, as per operating procedures separately formulated.
4.2.3
No important element of the State grid shall be deliberately opened
or removed from service at any time, except when specifically instructed
by the SLDC or with specific and prior clearance of the SLDC. The list of
such important grid elements on which the above stipulations apply shall
be prepared and be available at the SLDC. If any opening / removal of any
important element of the grid under an emergency situation as mentioned
in 4.2.2 (i) & (ii) takes place, the same shall be communicated to the
SLDC at the earliest possible time after the event.
4.2.4
Any tripping, whether manual or automatic, of any of the above elements
of State grid shall be precisely intimated by the concerned entities to
the SLDC as soon as possible, preferably within ten minutes of the event.
The reason (to the extent determined) and the likely time of restoration
shall also be intimated. All reasonable attempts shall be made for the elements'
restoration as soon as possible. Similarly any incident of outage significantly
affecting the system of any agency will be intimated to the agency by SLDC
within the above time.
4.2.5
All generating units, which are synchronized with the grid, irrespective
of their ownership, type and size, shall have their governors in normal
operation at all times. If any generator of over 50 MW rating is required
to be operated without its governor in normal operation, the SLDC shall
be immediately advised about the reason and duration of such operation.
All governors shall have a droop between 3% and 6%.
4.2.6
Facilities available with load limiters, Automatic Turbine Run up
System (ATRS), turbine supervisory control, coordinated control system,
etc., shall not be used to suppress the normal governor action. No dead
bands and / or time delays shall be deliberately introduced.
4.2.7
All generating units, operating at or up to 100% at their MCR shall
normally be capable of (and shall not in any way be prevented from) instantaneously
picking up five percent (5%) extra load as soon as possible but preferably
within five (5) minutes when frequency falls due to a system contingency.
However, for existing generating units (generating units of COD up to 31.12.2005),
these should be within the technical limits stipulated by the manufacturer.
The generating units operating at above 100% of their effective MCR shall
not be prevented from going at least up to 105% of their effective MCR when
frequency falls suddenly. After an increase in generation as above, a generating
unit may slide back to the original level at a rate of about 1% per minute,
in case continued operation at the increased level is not sustainable. Any
generating unit (synchronized with the
State grid) of over fifty (50) MW size, not
complying with the above requirement,
shall be kept in
operation only after obtaining the permission of the SLDC. However,
the entity can make up the corresponding shortfall in spinning reserve by
maintaining an extra spinning reserve on the other generating units of the
entity.
4.2.8
The recommended rate for changing the governor setting, i.e. supplementary
control for increasing or decreasing the generation sent out for all generating
units, irrespective of their types and sizes, would be 1% per minute or
as per manufacturer's limits. However, if frequency falls below 49.5 Hz,
all partly loaded generating units shall pick up additional load at a faster
rate, according to their respective capability.
4.2.9
Except under an emergency, or when there is need to prevent an imminent
damage to personnel and equipment, no entity shall suddenly reduce its generating
unit output by more than 100 MW without prior intimation to and consent
of the SLDC, particularly when frequency is falling or is below 49.0 Hz.
Similarly, no entity shall cause sudden increase in its load by more than
100 MW without prior intimation to and consent of the SLDC.
4.2.10 All
generating units shall normally have their AVRs in operation, with appropriate
settings. In particular, if a generating unit above 50 MW size is required
to be operated without its AVR in service, the SLDC shall be immediately
intimated about the reason and duration, and its permission obtained. Power
System Stabilizer (PSS) in AVRs of generating units (wherever provided),
shall be got properly tuned by the respective generating unit owner as per
plan prepared for the purpose by the SLCF from time to time. The STU will
be allowed to carry out checking of PSS and further tuning it, wherever
considered necessary.
4.2.11 Provision
of protections and relay settings shall be coordinated periodically throughout
the State grid, as per a plan to be separately finalized by the STU in coordination
with all entities and RPC.
4.2.12 All
entities shall ensure that the grid frequency always remains within the
49.0 - 50.5 Hz band.
4.2.13
All entities shall provide
automatic under-frequency load shedding in their respective systems, to
arrest frequency decline that could result in a collapse / disintegration
of the grid, as per the plan separately finalized by the SLCF, and shall
ensure its effective application to prevent cascaded tripping of generating
units in case of any contingency. All entities shall ensure that the under-frequency
load shedding / islanding schemes are functional and no under-frequency
relay is by-passed or removed without prior consent of the SLDC.
4.2.14
All entities shall also facilitate
identification, installation and commission of system protection schemes
(including inter-tripping and run-back) in the State’s State Grid to protect
against situations such as voltage collapse and cascading. Such schemes
would be finalized by the concerned SLCF forum, and shall be kept in service.
The SLDC shall be promptly informed in case any of these is taken out of
service.
4.2.15 Procedures
shall be developed to recover from partial / total collapse of the grid
and periodically updated in accordance with the regulation 4.8. These procedures
shall be followed by all the entities to ensure consistent, reliable and
quick restoration for which the SLDC shall co-ordinate with all entities.
4.2.16 Each
entity shall provide adequate and reliable communication facility internally
and with the SLDC and with other entities, if required, to ensure exchange
of data / information necessary to maintain reliability and security of
the grid. Wherever possible, redundancy and alternate path shall be maintained
for communication along important routes, e.g. SLDCs to ALDCs and / or generating
stations.
4.2.17 The
entities shall furnish on request information / data including disturbance
recorder / sequential even recorder output etc., to the SLDC for purpose
of analysis of any grid disturbance / event. No State entity shall block
any data/ information required by the SLDC for maintaining reliability and
security of the grid and for analysis of an event.
4.2.18 All
entities shall make all possible efforts to ensure that the grid voltage
always remains within the following operating range as specified for different
equipment.
Nominal Maximum Minimum
Voltage in (kV rms)
400 420 380
220 231 209
132 145 119
66 72 60
4.3 Demand Estimation for Operational Purposes:
The SLDC shall develop methodologies / mechanisms for daily / weekly /
monthly / yearly demand estimation (MW, MVAR and MWh) mainly based on the
data furnished by the Distribution Licensees for operational purposes. The
data for the estimation shall also include load shedding, power cuts etc.
The SLDC shall also maintain historical database for demand estimation,
which shall also take into account weather forecast appropriately. The demand
estimates are to enable the SLDC to conduct system studies for operational
planning purposes. While the demand estimates for operational purposes is
to be done on a daily, weekly, monthly basis initially, as deemed fit by
the SLDC and within one year, appropriate mechanism and facilities at the
SLDC shall be created at the earliest to facilitate on-line estimation for
daily operational use.
4.4 Demand Control:
4.4.1 Manual Demand Disconnection:
4.4.1.1 The
entities shall endeavor to restrict their net drawal from the grid to within
their respective drawal schedules whenever the system frequency is below
49.5 Hz. When the frequency falls below 49.0 Hz., requisite load shedding
(manual) shall be carried out to curtail the over drawal. Such load shedding
and also automatic UFR operation shall be pre planned for each level of
under frequency as per the guidelines as specified in Regulations of the
Commission or stipulated in any of the Commission’s order, if any and where
applicable.
4.4.1.2 Further,
in the case of certain contingencies and / or threat to system security,
the SLDC may direct the sub stations/distribution licensee to decrease its
drawal by a certain quantum. Such directions shall immediately be acted
upon.
4.4.1.3 Each
entity shall make such arrangements that will enable manual demand disconnection
to take place, as instructed by the SLDC under normal and / or contingent
conditions.
4.4.1.4 The
measures taken to reduce the entities' drawal from the State grid shall
not be withdrawn as long as the frequency / voltage remains at a low level,
unless specifically permitted by the SLDC / ALDC. If required, necessary
rescheduling of drawal for the entities shall be done by SLDC.
4.4.2
Load Shedding Policy:
In the case of shortage of power availability with respect to demand,
the ALDC shall resort to shedding the load of different feeders on economic
principle till the Commission specifies any policy in this matter through
notification.
4.4.3
Regulating Supply, Distribution,
Consumption or Use:
i)
The SLDC / ALDC will monitor,
regulate and submit report to the Commission as per order under section
23 of the Act.
ii)
In the case of shortage of supply, the Commission
in consultation with the SLDC / ALDC, may impose restriction on any consumer
or class of consumers or any feeder in drawal of power, including zero drawal,
for any time / duration of the day for a period as may be decided by the
Commission.
4.5 Periodic Reports:
4.5.1 A weekly report shall be submitted by the SLDC to the Commission, the
STU, licensees and generating companies of the State and shall cover the
performance of the State grid for the previous week. The weekly report shall
contain the following:
(i)
Frequency profile:
Maximum and Minimum frequency recorded daily on 15 minutes time block
basis and also average frequency during peak, off-peak and normal period;
(ii)
Voltage profile: The Voltage
profile of 132 KV and above substations;
(iii)
Major Generation and Transmission
outages;
(iv)
Transmission constraints;
(v)
Daily demand profile consisting
of:
(a)
Daily maximum demand (MW) with
corresponding frequency (HZ) and energy (MU) with corresponding average
frequency;
(b)
Daily load shedding at peak
hours (MW);
(c)
Daily load shedding in MU;
(d)
Daily technical interruption
losses in MW at peak hours;
(e)
Daily technical interruption
losses in MU
(vi)
Daily Generation Performance
Status:
Generating station wise daily schedule for availability declared, actual
generation, non-drawal by the system (if any), reason for non-drawal, reason
for less generation;
(vii) Instances of persistent
/ significant non-compliance of WBEGC;
(viii) Monthly load duration
curve with date;
(ix)
Demand and load for the days of month of maximum demand and minimum
demand.
4.5.2 Other Reports:
The SLDC shall also prepare a quarterly report, which shall bring out
the system constraints, reasons for not meeting the requirements, if any,
of security standards and quality of service, along with details of various
actions taken by different agencies, and the agencies responsible for causing
the constraints. The convenor of the SLCF shall arrange adding of the monthly
meeting of the Forum(s).
4.6 Operational Liaison:
4.6.1 Exchange of information, in relation to operations and / or events on the
total State Grid, which have had or will have an effect on the State Grid
or
The operational liaison generally relates to notifying of what is expected
to happen or what has happened and does not relate to the reasons of the
same. The operational liaison function is a mandatory built-in hierarchical
function of the SLDC and entities, to facilitate quick transfer of information
to operational staff. It will correlate the required inputs for optimization
of decision-making and actions.
4.6.2 Procedure for Operational Liaison:
(i)
Operations and events on the State grid:
Before any operation is carried out on the State Grid, the SLDC shall
inform each entity, whose system may, or will, experience an operational
effect, and give details of the operation to be carried out. Immediately
following an event in the State Grid, the SLDC shall inform each entity,
whose system may, or will, experience an operational effect following the
event and give details of what has happened in the event but not the reasons
why.
(ii)
Operations and events on an entity's system:
Before any Operation is carried out on an entity system, the entity shall
inform the SLDC, in case the State grid may, or will, experience an operational
effect, and give details of the operation to be carried out. Immediately
following an event on an entity system, the entity shall inform the SLDC,
in case the State grid may, or will, experience an operational effect following
the event, and give details of what has happened in the event but not the
reasons why.
4.7 Outage Planning:
4.7.1 General:
The procedure for preparation of outage schedules for the elements
of the State Grid in a coordinated and optimal manner keeping in view the
State Grid operating conditions and the balance of generation and demand
in optimal level, requires following activities.
(i)
A list of elements of State
grid covered under these Regulations shall be prepared and be available
with the SLDC within
(ii)
Preparation of a coordinated
generation outage programme for the State grid, considering all the available
resources and taking into account transmission constraints, as well as,
irrigational requirements. The generation output and transmission system
should be adequate after taking into account the outages to achieve the
State Grid security standards;
(iii)
Preparation of annual outage
planning in advance for the current year and reviewed during the year on
quarterly and monthly basis after due discussion in the SLCF.
(iv)
Optimization of the transmission
outages of the elements of the State grid without adversely affecting the
grid operation taking into account the generation outage schedule, outages
of constituent systems and expected level of maintenance of system security
standards on such transmission outages.
4.7.2 Outage Planning Process:
(i)
The STU, generating companies
and the distribution licensees with generation shall provide the SLDC with
their respective proposed outage programs in writing for the next financial
year by 1st August each year. These shall contain identification
of each generating unit / line / inter connecting transformer, the preferred
date for each outage and its duration and where there is flexibility, the
earliest start date and latest finishing date.
(ii)
The SLDC shall then come out
with a draft outage programme for the next financial year by 15th
November each year for the State grid taking into account the available
resources in an optimal manner and the need to maintain security standards.
This will be done after carrying out necessary system studies and, if necessary,
the outage programmes shall be rescheduled. Adequate balance between generation
and load shall be ensured while finalizing outage programme.
(iii)
The SLDC shall inform the RPC
Secretariat of its proposed outages in writing by 30th November for each
financial year.
(iv)
The RPC secretariat shall then
come out with an outage programme for the next financial year for the Regional
Grid as per Grid Code.
(v)
The SLDC shall interact with
all users as may be necessary to review and optimize the outage plan, agree
to any changes and produce an acceptable co-coordinated generation and transmission
outage plan.
(vi)
The SLDC shall release the finally
agreed outage plan in the SLCF, which takes into account of regional and
user requirements, to all users by 1st March each year.
(vii)
The SLDC shall review the final outage plan quarterly in consultation
with the RLDC and the users, who shall be informed by the SLDC of any proposed
changes. Users’ requests for additional outages will be considered by the
SLDC and accommodated to the extent possible. The SLDC shall inform users
promptly of any changes that affect them.
(viii)
In case of emergency in the
system viz., loss of generation, break down of transmission line affecting
the system, grid disturbance, system isolation, the SLDC, may conduct studies
again before clearance of the planned outage.
(ix)
The SLDC is authorized to defer
the planned outage in case of any of the following:
(a)
major grid disturbance;
(b)
system isolation;
(c)
black out in a constituent system;
(d)
any other event in the system that has
an adverse impact on the system security by the proposed outage.
(x)
Each entity shall obtain the
final approval from the SLDC prior to availing an outage.
4.8 Recovery Procedures:
4.8.1
Introduction:
The RLDC and the SLDC shall co-ordinate
with each other to determine the extent of the problem in case there is
any contingency crisis arising out of a total or a partial blackout of the
State Grid or the Regional Grid. The SLDC shall advise all users of the
situation and follow the strategy as outlined below for restoration.
Users’ employees’ persons authorised for
operation and control shall be available at Users’ end for communication
and acceptance of all operational communications throughout the contingency.
Communication channels shall be restricted, as far as possible, to operational
communications only till normalcy is restored.
4.8.2 Total
Regional Blackout:
The SLDC shall instruct all relevant generating
stations with black start capability to commence their pre-planned Black
Start Procedure. The SLDC may require the CPPs to extend start-up power
supply to generating stations as may be feasible.
The SLDC shall prepare the STS for restoration
by creating discrete power islands with no interconnection. Close co-ordination
with concerned entities shall be maintained during such restoration process.
Generating stations, to whom start up power supply is made available, shall
sequence their start up to match their auxiliary power demand with supply
available.
Generating stations shall inform the SLDC
as generating units become available to take load, in order that the licensee
may assess the MW demand, which the generating unit is likely to pick up
on circuit breaker closure.
The SLDC shall co-ordinate with generating
stations and distribution licensees to:
(i)
form discrete power islands with one generating unit feeding some local
demand;
(ii)
extend islands by adding more generating units and more demand in a coordinated
manner maintaining load generations balance;
(iii)
synchronize islands to form a larger, more stable island.
The SLDC shall, taking into account sites
where system synchronizers are available, gradually extend the synchronization
until all demand is restored.
The SLDC shall utilize any regional or
Inter-State assistance available, if appropriate, at any time to assist
in the above process.
During recovery, priority of withdrawal
of restriction on power drawal shall be as per policy of 4.4.3.
4.8.3
Responsibilities:
(i)
Detailed plans and procedures for restoration of the
State grid under partial / total black out shall be developed by the SLDC
in consultation with all entities and the RLDC / the RPC and shall be reviewed
/ updated annually and be communicated to all transmission and distribution
licensee and generating companies.
(ii)
Detailed plans and procedures for restoration after
partial / total black out of each constituent's system within the State,
shall be finalized by the constituent concerned in coordination with the
SLDC. The procedure shall be reviewed, confirmed and / or revised once every
year.
(iii)
List of generating stations with black start facility,
inter-State, synchronizing points and essential loads to be restored on
priority, shall be prepared and be available with SLDC.
(iv)
The SLDC is authorized during the restoration process
following a black out, to operate with reduced security standards for voltage
and frequency as necessary in order to achieve the fastest possible recovery
of the grid.
(v)
The SLDC shall always endeavour to restrict
its net drawal from the Inter-State / regional grid within the respective
drawal schedules of entities by directing appropriate instruction to the
entities, whenever the system frequency is below 49.5 MHz. When the frequency
falls below 49.0 MHz, requisite load shedding shall be carried out in the
concerned licensed area to curtail the over-drawal.
(vi)
The SLDC is required to advise the entities
about their respective entitlement from allocation / share of generation
stations, collection of their requisition, compiling them into State’s total
requisition from central sector allocation, etc. in accordance with the
principle laid down by the policy of the State Government or Government
of India.
4.8.4 Special Considerations:
During the restoration process following
regional blackout conditions, normal standards of voltage and frequency
shall not apply.
A list of essential loads and priority
of restoration shall be prepared by each entity in line with regulation
4.4.3.
Distribution Licensees with essential
loads shall separately identify non-essential components of such loads,
which may be kept off during System contingencies. Distribution Licensees
shall draw up an appropriate schedule with corresponding load blocks in
each case. The non-essential loads can be put on only when system normalcy
is restored, as advised by the SLDC.
All users shall pay special attention
in carrying out the procedures so that secondary collapse due to undue haste
or in-appropriate loading is avoided.
Despite the urgency of the situation,
careful, prompt and complete logging of all operations and operational messages
shall be ensured by all users to facilitate subsequent investigation into
the incident and the efficiency of the restoration process. Such
investigation shall be conducted promptly after the incident.
4.9 Operational
Event / Accident Reporting:
4.9.1 Reportable
Incidents:
Typical examples of reportable incidents
that could affect the grid are the following:
(i)
Exceptionally high/low system
voltage or frequency;
(ii)
Serious equipment problem i.e.
major circuit, transformer or bus bar fault;
(iii)
Loss of major generating unit;
(iv)
System split, transmission system
breakaway or black start;
(v)
Major fire incidents;
(vi)
Major failure of protection;
(vii)
Equipment and transmission line
overload;
(viii)
Excessive Drawal deviations
4.9.2 Reporting Procedure:
(i)
All reportable incidents occurring
in lines and equipment of 33 kV and
above at grid sub-stations and generating stations shall promptly be reported
orally / message by the user whose equipment has experienced the incident
to any other significantly affected Users and to SLDC.
(ii)
Depending on the nature of incidence,
the SLDC may ask for a preliminary as well as detailed written report, which
shall be submitted within 48 hours in case of preliminary report and in
case of detailed report it shall be submitted within 7 days.
(iii)
In the case of an event occurring
in EHV system and generating equipment which was initially reported by a
constituent, the constituent shall give a written report within a week.
(iv)
The SLDC may call for a report
from any user on any reportable incident affecting other users and the entity
in case the same is not reported by such user whose equipment might have
been the source of the reportable incident.
(v)
The above shall not relieve any
user from the obligation to report events in accordance with Safety Regulations.
(vi)
The
format of such a report shall be as agreed at the SLCF and approved by the
Commission, but will typically contain the following information: -
Location of incident;
Date and time of incident;
Plant or equipment involved;
Supplies
interrupted and duration if applicable;
Amount of generation lost if applicable;
Brief description of incident;
Estimate
of time to return to service;
Name
of originator.
4.9.3 The standard reporting form would be as follows:
INCIDENT
REPORTING
Date:.........
Time:…......
1.
Date and time of incident,
2.
Location of incident,
3.
Type of incident,
4.
System parameters before the
incident (Voltage, Frequency, Flows, Generation, etc.),
5.
System parameters after the incident;
6.
Network configuration before
the incident,
7.
Relay indications received and
performance of protection;
8.
Damage to equipment,
9.
Supplies interrupted and duration,
if applicable;
10.
Amount
of Generation lost, if applicable,
11.
Estimate
of time to return service,
12.
Cause
of incident;
13.
Any
other relevant information and remedial action taken,
14.
Recommendations
for future improvement/repeat incident;
15.
Name
of the Organisation;
4.9.4 Major Failure:
Following a major failure,
the licensee and other users shall co-operate to inquire and establish the
cause of such failure and produce appropriate recommendations. Licensee/users
shall report the major failure to the Commission immediately for information
and shall submit the enquiry report to the Commission within 2 (two) months
of the incident.
4.9.5 Accident Reporting:
Reporting of accidents
shall be in accordance with the Section 161 of Electricity Act, 2003. In
both fatal and non-fatal accidents, the report shall be sent to the Electrical
Inspector in the prescribed form and to such other authorities as the State
Government may, by general or special order, direct.
CHAPTER
5
SCHEDULING
AND DESPATCHING
5.1 Objective:
Procedures to be adopted after introduction of intra-State ABT for scheduling
of injection by beneficiaries including all generating agencies connected
with the STS, injected share of ISGS and scheduling of drawal by all licensees
connected to the STS of the State on a daily basis are dealt with herein.
5.2 Demarcation of responsibilities:
(i)
In pursuance to Intra-State
Availability Based Tariff (ABT) specified in Tariff Regulations, the SLDC,
shall have the total responsibility for scheduling / despatching by generating
stations of generating companies, the CPPs and Open Access Customers concerned
as per Tariff Regulations connected to the State grid, the drawal/injection
by the entities, the drawal from the ISGS and the inter-State interchanges
of traded power or under sub-section (5) of section 64 of the Act, if there
is any.
(ii)
The SLDC, if required, through
STU, shall always endeavour to restrict net drawal from generating stations
and others within their respective drawal schedules.
(iii)
The generating stations and
inter-state injectors, under Intra-State ABT, connected to the STS shall
be responsible for power injection generally according to the daily schedule
advised to them by the SLDC.
(iv)
However, such generating stations
may deviate from the given injection schedules depending on the plant and
system conditions. In particular, they would be allowed / encouraged to
generate beyond the given injection schedule under deficit conditions as
per guidance of the SLDC.
(v)
Provided that when, the frequency
is higher than 50.5 Hz, the actual net injection shall not exceed the scheduled
injection for that hour. Also while the frequency is above 50.5 Hz, the
generating stations may back down their generation in concurrence with the
SLDC to restrict the frequency rise. When the frequency falls below 49.5
Hz, the lifting of backing down should be as per guidance of SLDC.
(vi)
However, notwithstanding the
above, the SLDC may direct the beneficiaries to increase / decrease their
injection / drawal in case of contingencies e.g. overloading of lines /
transformers, abnormal voltages, threat to system security. Such directions
shall immediately be acted upon.
(vii)
For all outages of generation
and transmission system, which may have an effect on the State grid, all
entities shall co-operate with each other and co-ordinate their actions
as per the procedures finalized separately. In particular, outages requiring
restriction of generation, which a beneficiary can receive (and which may
have a commercial implication) shall be planned carefully to achieve the
best optimization.
(viii)
The entities shall furnish
to the SLDC all requisite information for billing purposes.
(ix)
All entities shall abide by
the concept of frequency linked load dispatch and pricing of deviations
from schedule i.e. unscheduled interchanges. All generating units of the
entities shall normally be operated according to the standing frequency
linked load dispatch guidelines issued by the SLDC to the extent possible,
unless otherwise advised by the SLDC.
(x)
The SLDC shall be responsible
for intra-State energy accounting as per the Balance and Settlement Code
as specified in Tariff Regulations, and all entities shall extend the necessary
assistance to the STU personnel in timely collection of metered data.
5.3 Scheduling and Despatch Procedure:
The general methodology for scheduling and
calculating availability and capacity index shall be as under:
(i)
By
(ii) The declaration shall be for the capacity of the generating station to deliver ex-bus MW for the next day either as one figure for the whole day or as different figures for different periods of the day along with maximum available capacity (MW) and total energy (MWh) ex-bus to the SLDC. The capacity as declared by the generating stations, also referred to as the declared capacity, shall form the basis of injection scheduling.
(iii) For hydro-generating stations, the declaration should also include limitation on generation during specific time periods, if any, on account of restriction on water use due to irrigation, drinking water, industrial, environmental considerations, etc.
(iv) At the time of declaration of generation for injection, the pumped storage hydro-generating station shall also declare its drawal schedule along with the sources from where power will be drawn for its pumping mode operation. For both these purposes, the formats of Annexure - III and Annexure - IV shall be used.
(v) For hydro-generating stations transformation losses means the losses due to transformation of firm generation voltage to transmission voltage and is about 0.5% of energy generated.
(vi)
The SLDC shall receive ISGS
schedule of the next day from RLDC within
(vii) While giving requisition of drawal, the licensee or beneficiary shall also show block-wise projected demand under normal conditions along with reasons of restriction in drawal, if any, and its quantum. This requisition shall be given as per format in Annexure - IV. This requisition shall also indicate separately quantum of power to be supplied to persons, other than beneficiaries under long-term and short-term power selling agreement and also short-term sale of incidental surplus power after meeting fully the demand of the area of supply.
(viii) In case of any entity, the requisition of drawal / injection schedule shall be submitted by their respective ALDC on behalf of them. While submitting such requisition or schedule it shall take into consider the requirement of other entities as explained in item (ix) below. Such Intra-State ABT scheduling shall be applicable to all the entities as specified in the regulation 5.1.2 of Tariff Regulations.
(ix) All other entities on whom these Regulations are applicable shall give their drawal requisitions along with the source of supply against such drawals and corresponding injection schedules from such sources as applicable. For this purpose, formats of Annexure - IIII and Annexure - IV shall be used. These entities shall submit their above drawal requisition / injection schedule to the ALDC or SLDC, on whose area of supply their drawals or injections are taking place. In case of such submission to the ALDC, the ALDC shall reflect the drawal requisition and injection schedule in its corresponding drawal requisition and injection schedule to be submitted to the SLDC.
(x) The drawal requisition of a beneficiary or a licensee or a pumped storage hydro-generating station shall show its drawal from those generating stations and licensee only with whom there is power purchase agreement and drawal against each such generating stations and licensee shall be shown separately.
(xi) Based on the requisitions given by the beneficiaries and different entities and taking into account technical limitations on varying the generation and transmission system constraints, if any, the availability of central sector allocation / share, the relevant issues like open access and trading of power, etc. in the regional schedule, the SLDC shall prepare the economically optimal injection schedules for generating stations of generating company, distribution licensees and other entities and also drawal schedules for distribution licensees and other entities. The SLDC shall communicate the same to the generating stations and the beneficiaries.
The SLDC shall also communicate the final drawal schedule of power to the pumped
storage hydro-generating station for its pumping operation and also confirm
the schedule to the concerned source from where power will be drawn.
(xii)
While finalizing the above
daily generation schedules for the generating stations, the SLDC shall ensure
that the same are on merit order basis as far as possible, operationally
reasonable, particularly in terms of ramping / sliding rates and the ratio
between minimum and maximum generation levels.
The SLDC shall also formulate the procedure for meeting contingencies both in the long run and in the short run, and detailed scheduling procedure in a surplus and shortage system in its monthly meeting with the licensees.
(xiii)
The generating agencies connected
to STS or agencies injecting power in State Grid shall inform any modification
/ changes to be made in station wise foreseen capabilities, if any, to the
SLDC by
(xiv)
Based on the surplus, if any,
the concerned beneficiaries may arrange for supply such surplus power through
day ahead transaction under Open Access Regulations or any Inter-State supply.
Such arrangement or the modification, if any, shall be intimated to the
RLDC by the SLDC by
(xv)
The SLDC shall inform the final
injection / drawal schedule for the next day to all concerned by
(xvi)
In the event of any contingency,
during the course of the day of operation, the SLDC or any generating station
of any generating company connected to the STS or any entity may revise
its injection and drawal schedule and its foreseen capability, drawal/export,
for the balance period of the day. The SLDC shall then revise the concerned
'drawal schedule' and 'dispatch schedule' in consultation with the concerned
beneficiaries and issue the same. All such revisions shall be effective
one hour after the first advice is received by the SLDC.
(xvii) While finalizing the drawal and injection schedules as above, the SLDC shall also check that the resulting power flows do not give rise to any transmission constraint. In case any impermissible constraint is foreseen, the SLDC shall moderate the schedules to the required extent, under intimation to the beneficiaries concerned. The revised schedule shall be made effective from the fourth time blocks counting the issuing time as the first time block. In case of any grid disturbance, the scheduled injection and scheduled drawal of all beneficiaries shall be deemed to have been revised to be equal to their actual injection / drawal for all the time blocks affected by grid disturbance.
(xviii) In the case of a forced outage of a unit, the SLDC shall revise the schedules on the basis of revised declared capacity. The revised declared capacity and the revised schedules shall become effective from the 4th time block, counting the time block in which the revision is advised by the generator to be the first one.
(xix) In the event of a bottleneck in evacuation of power due to any constraint, outage, failure or limitation in the STS, associated switchyard and sub- stations owned by the Licensees necessitating reduction in injection by any beneficiary, the SLDC shall revise the schedules which shall become effective from the 4th time block, counting the time block in which the bottleneck in evacuation of power has taken place to be the first one. Also, during the first, second and third time blocks of such an event, the scheduled injection shall be deemed to have been revised to be equal to actual injection, and the scheduled drawals / injection of the beneficiaries and all other entities on whom these Regulations is applicable, shall be deemed to have been revised to be equal to their actual drawals.
(xx) In the case of any grid disturbance, scheduled injection and scheduled drawal of the beneficiaries and all other entities on whom these Regulations are applicable, shall be deemed to have been revised to be equal to their actual injection / drawal for all the time blocks affected by the grid disturbance. Certification of grid disturbance and its duration shall be done by the SLDC within 24 hours of the grid disturbance. The SLDC shall notify all the entities in the grid about the period of such grid disturbance and the effected portion of the grid system in detail.
(xxi) If any running unit(s) of Bandel Thermal Power Station’s first four units, or of Santaldih Thermal Power Station goes / go out of operation from running condition at any block of time, then from the next block of time, the generation of such generating plants shall be considered as scheduled generation up to 6th block or till revised schedule is obtained, whichever is less, and the injection schedule by those generating stations shall be modified by SLDC accordingly.
(xxii)
Revision of declared capacity by
the generation station(s) and requisition by beneficiary(ies) for the remaining
period of the day or part of the day or injection / drawal of the entities
as per agreement shall also be permitted with advance notice. Revised schedules/declared
capacity or injection / drawal schedule in such cases shall become effective
from the 6th time block, counting the time block in which the request for
revision has been received in the SLDC to be the first one.
(xxiii)
If, at any point of time, the SLDC
observes that there is need for revision of the schedules in the interest
of better system operation, it may do so on its own, and in such cases,
the revised schedules shall become effective from the 4th time block, counting
the time block in which the revised schedule is issued by the SLDC to be
the first one.
(xxiv)
For any revision of a scheduled injection, including post facto deemed revision,
there shall be a corresponding revision of scheduled drawals of the beneficiaries.
The SLDC shall issue final schedule of the day by
(xxv)
On completion of the operating
day, by 24.00 hours, the schedule finally implemented during the day (taking
into account all before-the fact changes in dispatch schedule of generating
stations and drawal schedule of the users) shall be issued by the SLDC.
This schedule shall be the datum for commercial accounting. The average
ex-bus capability for each of the generating stations connected with the
STS shall also be worked out based on all before-the-fact advice to the
SLDC.
(xxvi)
While making or revising its declaration of
capacity, the generator shall ensure that the declared capacity during peak
hours is not less than that during other hours. However, exception to this
may be allowed in case of tripping/re-synchronization of units as a result
of forced outage of units. The peak-hours shall be as applicable for generating
station as per Tariff Regulations.
(xxvii)
The scheduled injection and actual injection
for generation station shall be ex-bus generation at the generating station.
For beneficiaries and all other entities on whom these Regulations are applicable,
the scheduled and actual net drawals shall be at their respective receiving
points as mentioned in the PPA.
(xxviii) For calculating the net drawal schedules of beneficiaries and all other entities on whom these Regulations are applicable, the applicable intra-State transmission losses shall be apportioned to their drawal schedules for the time being.
Provided that a refinement may be specified by the Commission in future
depending on the preparedness of the SLDC.
(xxix)
Drawal / injection schedules issued/revised
by the SLDC shall become effective from designated time block. Every endeavor
shall be made by the SLDC to communicate the revision to the concerned entities
unless there are extra-ordinary circumstances for only upon such communication
the time block shall be reckoned to commence.
(xxx)
A procedure for recording the communication
regarding changes to schedules duly taking into account the time factor
shall be evolved by the STU.
(xxxi)
Since variation of generation in purely run-of-river
hydro generating stations may lead to spillage, these shall be treated as
must run stations. The maximum available capacity in each time block, duly
taking into account the over load capability, shall be equal to or greater
than that required to make full use of the available water of that time
block.
The run-of-river hydro-generating station with pondage, storage type hydro-generating
stations and pumped storage hydro-generating stations are designed to operate
during peak hours to meet system peak demand. The maximum available capacity
of a station declared for the day shall be equal to the installed capacity
including overload capability, minus auxiliary consumption and transformation
losses, corrected for the reservoir level. The SLDC shall ensure that generation
schedules of such type of stations are prepared and the stations dispatched
for optimum utilization of available hydro energy except in the event of
specific system requirements/constraints.
(xxxii)
The SLDC shall schedule and control the
overall generation and injection of power in the STS in the specified manner
after giving due preference to run-of-river hydro-generating station, canal
based hydro-generating station, hydro generating station where water level
is at peak reservoir level and inflow of water goes as a waste, and any
other generating station where energy potential of the generating station,
if unutilized, goes waste.
(xxxiii)
The SLDC shall properly document all above
information i.e. station-wise foreseen ex-power plant capabilities advised
by the generating stations, the drawal schedule indented by the beneficiaries,
all schedules issued by the SLDC and all revisions / updating of the above.
(xxxiv)
The procedure for scheduling, carried out
by SLDC shall be open to all entities for any checking / verification. In
case any mistake / omission is detected, the SLDC shall forthwith make a
complete check and rectify the same.
(xxxv)
If required the SLDC may ask for the additional
information besides those in Annexure – III & IV from respective persons
concerned. In case of requirement of such additional information on regular
basis, SLDC shall obtain prior approval from the Commission.
(xxxvi)
While availability declaration by the generating
stations may be a resolution of one MW and one MWHr all entitlement requisitions
and schedules shall be rounded off to the nearest decimal, to have a restriction
of 0.1 MW.
5.4 Reactive Power
and Voltage Control:
(i)
Regarding VAR drawal / absorption
from Inter-State Grid, the SLDC has to follow the Grid Code.
(ii)
All the distribution licensees,
transmission licensees and the STU are expected to provide local VAR compensation
such that they do not draw VARs from the grid. VAR compensation has to commence
in the following order:
(a)
Consumer end,
(b)
Distribution transformer end,
(c)
At the substations end of 6/11
/ 33 kV distribution feeders,
(d)
Substations of STU,
(e)
Generating stations.
(iii)
While tap changing on all 400 / 220 kV ICTs of CTU shall be done
as per the instruction of the RLDC while tap changing of other ICTs shall
be done as per the instructions of the SLDC.
(iv)
The generating stations shall generate / absorb reactive power as
per instructions of the SLDC, within the capability limits of the respective
generating units. No payments shall be made to the generating companies
for such VAR generation / absorption.
(v)
The SLDC may direct a beneficiary to curtail its VAR drawal/ injection
in case security of the grid or safety of any equipment
is endangered.
(vi)
At interchange point the VAR drawal/ injection shall be minimum when
voltage at that point is below 97% or above 103%.
CHAPTER 6
NON-COMPLIANCE
6.1 In pursuance to sub-sections (2), (4) and
(5) of section 33 of the Act, every
licensee, generating company, generating station, EHT S/S and any other
entity connected with the operation of the State Grid shall comply with
directions issued by the SLDC. If
any dispute arises with reference to the safe, secure and integrated operation
of the State grid or interpretation of clauses of State Grid Code, or in
relation to any direction given by the SLDC, it shall be referred to the
WBERC for decision. Pending decision of the Commission, the concerned party
raising the dispute shall comply with direction of the SLDC. The WBERC,
in turn, after due process may order the defaulting entity for compliance
or otherwise. The non-compliance of the same may lead to penal
action, which includes termination of connectivity agreement and de-linking
from the State Grid.
6.2 In the case of non-payment of dues i.e.
bills by any beneficiary, the affected entity shall report the matter to
the SLDC. The SLDC shall verify the facts and take up
the matter with the defaulting entity for paying up of the dues. In case of non-compliance by the defaulting
entity, the WBERC shall be informed by the SLDC, whereupon the WBERC shall
initiate necessary action,
6.3 Any entity that has been accused of non-compliance
of any direction of any Appropriate Commission and has its connection disconnected
with any grid by virtue of any order
of the Appropriate Commission, shall not be allowed any connectivity with
State Grid unless the original dispute is settled.
CHAPTER 7
COMMERCIAL ISSUES
7.1
The summation of input meter readings at the connection
points of the STS with generating stations, entities engaged in distribution
of electricity and inter-connection points with the CTU and other entities
gives the total flow into the STS. Similarly,
the summation of export at the connection points of the STS with generating
stations, entities engaged in distribution of electricity and inter connection
points with the CTU and other entities gives the total outflow from the
STS. The difference between the
inflow and outflow is the transmission loss of the STS. As the connection points with distribution entity
may be large in number, initially it may not be possible to apply the above
principle to determine transmission loss.
In such an event several load flow studies representing different
load conditions covering at least three seasons and three hours of the day
may be carried out to determine the transmission loss.
The transmission losses determined either way shall be apportioned
to the distribution entity consuming power and energy from the STS network
and added to their metered drawal, to arrive at the billing figure.
7.2
Any variation between an actual injection or an actual
drawal and the scheduled injection or the scheduled drawal shall be accounted
for by SLDC as per Tariff Regulations. Weekly bills of variations shall be prepared
and issued by the SLDC. These bills
shall have high payment priority and the concerned entities shall make payment
of the billed amount within 10 days of billing date.
If the payments against the above bills are delayed, the defaulting
entities shall have to pay simple interest @ 0.04% for each day of delay. The interest so collected shall be paid to the
entities who were to receive the payment.
In case of continued payment default, the matter should be brought
to the notice of the WBERC by the SLDC.
7.3
Energy accounts shall be prepared by the SLDC on monthly
basis and shall be issued to all concerned entities within 3 clear working
days of the succeeding month.
7.4
All energy accounting
calculations carried out by the SLDC shall be open to all users for any
checking / verification. In case
any mistake is detected, the SLDC shall make a complete check and rectify
the mistake.
7.5
In matters concerning
VAR drawal / absorption (its rate and payment) from inter-State grid, the
SLDC has to follow Grid Code. VAR
drawal / absorption and payment for the same shall be settled between a
beneficiary and the pool account, or between the beneficiaries as applicable. The generating stations shall generate / absorb
reactive power as per instruction of the SLDC, within the capability limits
of the generating units. No payments
shall be made to generating companies for the same.
CHAPTER
8
POWER OF THE COMMISSION
TO AMEND, TO REMOVE DIFFICULTIES, DISPENSE WITH REGULATIONS AND REPEAL
8.1
Powers to remove difficulties:
8.1.1
If any difficulty arises in giving
effect to any of the provisions of these Regulations, the Commission may,
with reasons to be recorded in writing, direct the licensees, the consumers
or the applicants for Open Access, by general or special order, for taking
suitable action not inconsistent with the provisions of the Act, as may
appear to be necessary for removing the difficulty.
8.2
Power to Amend:
8.2.1
The Commission may, at any point
of time, at its sole discretion, vary, alter, modify, add or amend any provisions
of these Regulations.
8.3
Power to dispense with Regulations:
8.3.1
Nothing in these Regulations shall
be deemed to limit or otherwise affect the inherent powers of the Commission
to make such orders as may be necessary for meeting ends of justice or to
prevent the abuse of the process of the Commission.
8.4
Repeal:
8.4.1
The West Bengal Electricity Regulatory Commission (West Bengal
Electricity Grid Code) Regulations, 2006 issued under Notification No. 26/WBERC
dated
SITE RESPONSIBILITY
SCHEDULE
[See Regulation 3.3]
Name of Power Station / Sub-Station owner:
Tel. Number:
Fax Number:
Permanent Address:
| Item
of Plant / Apparatus |
Plant
Owner |
Responsibility
for |
Remarks |
|||
| |
|
Safety |
Control |
Operation |
Maintenance |
|
| |
|
|
|
|
|
|
| …kV Switchyard |
|
|
|
|
|
|
| All equipments including Bus bars |
|
|
|
|
|
|
| Feeders |
|
|
|
|
|
|
| |
|
|
|
|
|
|
| |
|
|
|
|
|
|
| Generating Units |
|
|
|
|
|
|
| |
|
|
|
|
|
|
| |
|
|
|
|
|
|
[See Regulation 3.6.5]
1. Name of Power Station
2. Station
type – Thermal (coal, gas, oil), Hydro (Reservoir type), ROR (with hours
of Storage / Pump Storage), GT/CCGT.
3. Station
capacity -
(i) Total capacity (ii) Number of units & size
4.1
Thermal Station –
(i) Rating of Boiler, Turbine
& major auxiliaries
(ii)
Peaking availability and peaking
capability
4.2
GT/CCGT –
(i) Natural gas / LNG / Oil
(ii)
Salient details of GT/CCGT
(iii)
Peaking availability & peaking
capacity
4.3
Hydro –
(i)
Schematic layout showing dam reservoir area, water conductor system,
fore bay, powerhouse etc.
(ii)
Rating of turbine & other major
equipment
(iii)
Reservoir data and operating table
(iv)
Operating head maximum & minimum
4.4
Captive power plant
(i) Salient details including
plant capacity & exchange of power.
5.1
Generators –
(i) Type
(ii)
Rating / MVA
(iii)
Voltage
(iv)
Speed
(v)
Inertia constant H (MW Sec/MVA)
(vi)
Rated P.F
(vii)
Reactive power capability
(viii)
S.C. ratio
(ix)
Xd, X1d,
X11d (Saturated
& Unsaturated)
(x)
Xq, X1q,
X11q (Saturated
& Unsaturated)
(xi)
T1do, T11do
(xii)
T1qo, T11qo
(xiii)
Stator resistant & leakage
reactance or Potier Reactance
(xiv)
Stator time constant
(xv)
Rated field current
(xvi)
Neutral grounding
(xvii)
Generator Capability Curve
6. Generators Transformer
(i)
Type
(ii)
Rated capacity / MVA
(iii)
Voltage ratio & vector group
(iv)
Tap changer range
(v)
On load / Off load tap changer
(vi)
Percentage impendence – Positive
& Zero Sequence
(vii)
Grounding of Generator Transformer
(viii)
X / R Ratio
7.1
Excitation –
(i)
Type of excitation
(ii)
Rated field voltage, maximum &
minimum field voltage
(iii)
Details of excitation loop block
diagram showing transfer functions
8. Governor System -
(i)
Governor droop
(ii)
Speeder motor setting range
(iii)
Governor block diagram showing
transfer functions & different time constant
(iv)
Dead band, if any.
9. Protection & metering -
(i)
Description of all relays &
protection system installed in generating unit.
(ii)
Description of all relays & protection
system installed on all outgoing feeders
(iii)
Full description of operational &
commercial metering schemes.
10. Operational parameters -
(i)
Minimum time required
to synchronize a generating unit from de-synchronization (hot start).
(ii)
Maximum time to
synchronize a unit from rest (cold start).
(iii)
The maximum load
(iv)
Maximum unit loading
& unloading rates.
1.1
Single line diagram of transmission
system down to 132/33 KV S/S.
(i)
Name of S/S
(ii)
Power Station connection
(iii)
Number & length of circuits
(iv)
S/S bus layout (
(v)
Power transformers
(vi)
Reactive compensation equipment
(vii)
Grounding arrangement
1.2
Transformer parameters – Rated
MVA, Voltage rating & vector group, Positive & zero sequence Impedance,
Tap Changer (on / off load) and range, Transformer Grounding and X/R Ratio.
1.3
Component details –
(i)
Circuit breaker, isolating switches,
current & potential transformers.
1.4
Relays & meters –
(i)
Relay protection for all transformers
and feeders
(ii)
Metering detail
1.5
Line parameters – Line designation,
Year of commissioning, Length of line (Km), Line capacity (Thermal &
surge impedance), No. of circuits, Per
unit circuit impedance on 100 MVA &
admittance values (positive & zero sequence).
Distribution
Data
1. Name
of S/S of STU from where connection shall be made.
1.2 Quantum of power (MW) /
MVA to be drawn / injected from / to of STU S/S and voltage and no. of circuits
required.
1.3 The
length and size of the feeder and no. of
distribution S/S connects to the feeder for supply of load to distribution
area.
1.4 Reactive compensation used to control reactive
drawal from STU, feeder-wise.
1.6
Details of protection & metering
for the feeders.
1.7
Type of Load or Load characteristic
(whether constant power or Voltage impendence, etc.)
Load forecast
Data
1. Consumer data – Furnish categories of
consumers, their nos., connected load.
2. Peak load and energy forecast
for each connection point / in the face point for each category of load
for each of the succeeding 10 years.
3. Methodology and assumptions on which forecast
made.
4. If supply is received from
more than one STU S/S, the S/S-wise break-up of peak load & energy projections
for each of succeeding 10 years with estimated daily load curve.
5. Details of bulk load 5 MW & above,
Voltage of supply, S/S from which is to be fed.
Annexure – III
INJECTION SCHEDULE
[See Regulation 5.3 (i), (iv), (ix)]
|
Block No. |
Time
in |
Proposed injection by entity in MW from own
generating station |
Proposed Injection by the entity from own
availability for other entities* |
Injection of power on behalf of other entities
as per 5.3 (ix) |
Total Injections (Outside own area of supply) |
| (1) |
(2) |
(3) |
(4) |
(5) |
[6 = (4+5)] |
| 1. |
00.00 hrs.
to 00.15 hrs. |
-------- |
-------- |
-------- |
-------- |
| 2. |
00.15 hrs. to 00.30 hrs. |
-------- |
-------- |
-------- |
-------- |
| 3. |
00.30 hrs. to 00.45 hrs. |
-------- |
-------- |
-------- |
-------- |
| 4. |
00.45 hrs. to 01.00 hrs. |
-------- |
-------- |
-------- |
-------- |
| 5. |
------ |
-------- |
-------- |
-------- |
-------- |
| ------ |
------- |
-------- |
-------- |
-------- |
-------- |
| ------ |
------- |
-------- |
-------- |
-------- |
-------- |
| 96. |
23.45 hrs. to 24.00 hrs. |
--------- |
--------- |
--------- |
--------- |
* Note: Destination wise injection is to be shown separately in separate column.
Annexure – IV
DRAWAL SCHEDULE
[See Regulation 5.3(iv), (vii), (ix)]
|
Projected Drawal (MW) From |
Projected Demand (MW) |
Schedule of Drawal for Open Access Customer
(OAC) |
Export
through Trading |
Gross requirement
of the Licensee for drawal |
|||||||||||
| Block No. |
Generating Company. |
Distribution Licensees
(State) |
Committed Inter-State
power supply under sub-section (5) of section 64 |
Electricity Trader
(including distribution licensee in Trading Mode) |
Total Drawal |
Without restriction |
With restriction |
Reasons of Restriction |
Name of Open Access
Source |
Proposed drawal |
Restricted to, if any |
||||
| Quantum |
Reason |
Outside State |
Within State |
||||||||||||
| |
(a) |
(b) |
(c) |
(d) |
(e) = (a + b +
c + d) |
(f) |
(g) |
(h) |
(i) |
(j) |
(k) |
(l) |
(m) |
(n) |
(o) = (e + k) = (g + m +
n+ k) |
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
| |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
By Order of the Commission
Place: Kolkata
Dated: 04.04.2007 (K. L. Biswas)
Secretary of the Commission